Asbestos management plan

For surveys on non-domestic property, after your asbestos survey is complete and the report (known as the ASBESTOS REGISTER) is issued, a companion document (the ASBESTOS MANAGEMENT PLAN), needs to be prepared.

Regulations 4, 6 and 7 of the Control of Asbestos Regulations 2012 refer.

Whilst the Asbestos Register sets out where the asbestos is, and what needs to be done with it, the Asbestos Management Plan sets out the way in which the various asbestos issues will be managed on site :

What needs to be done before refurbishment, demolition or major maintenance works. Also, sets out the Manager responsible, asbestos awareness training, re-inspection issues and systems to monitor contractors works on site etc…

Henfield house Asbestos management plan

Fire damaged house which had asbestos insulating board soffits